The New Rules of the Build: Ontario’s 2026 Construction Act Overhaul
Mandatory Holdbacks, Private Adjudication, and the End of the "Wait-and-See" Approach
The Executive Summary: As of January 1, 2026, the Ontario Construction Act has undergone a massive shift from "optional" to "mandatory" annual holdback releases. This, combined with a new 7-day "Deemed Invoice" rule, means that construction cash flow in Ontario is moving faster than ever. For Owners, Contractors, and Sub-trades, the "wait-and-see" approach is now a liability. This guide explores the technical details you need to maintain your project’s "Peace of Mind."
For decades, the construction industry in Ontario operated on a "long-tail" financial model. Money—specifically the 10% statutory holdback—was something you saw at the very end of a project, often years after your specific work was completed.
That era is over.
The 2026 Construction Act amendments represent a fundamental rewiring of the construction pyramid. The provincial government’s goal is clear: accelerate liquidity, reduce the "hoarding" of capital, and provide a private, expert-led path for dispute resolution. At Cabinet Sauvé Law, we know that for our clients, these changes are a double-edged sword. They offer better cash flow but demand a level of administrative precision that many firms aren't prepared for.
Section 1: The Mandatory Annual Holdback Release
The headline change for 2026 is the repeal of the "optional" system. Previously, under Section 26.1, an owner could choose to release holdback annually if the contract allowed for it. Most didn't.
Now, annual release is a statutory obligation. If your project lasts longer than one year, you are legally required to flow that 10% back down the chain on an annual basis.
The Precise 74-Day Cycle
To comply with the Act, Owners must now follow a strict chronological "rhythm" based on the anniversary of the contract:
- The Anniversary Trigger (Day 0): The clock starts on the date the contract was signed.
- The Publication Window (Day 0–14): Within 14 days of the anniversary, the Owner must publish a Notice of Annual Release of Holdback (Form 6) in a construction trade newspaper.
- The Preservation Period (Day 15–60): This 45-day window allows sub-trades to file a lien if they have unpaid claims from the previous year.
- The Payment Window (Day 60–74): If no liens are preserved, the Owner is legally obligated to release the accrued holdback to the Contractor.
Why this is a "Peace of Mind" issue: If an Owner misses the publication deadline, they could be found in breach of the Act, potentially triggering interest penalties and disrupting the entire downstream payment schedule.
Section 2: The New "Private Adjudication" Model
Since 2019, the Ontario Dispute Adjudication for Construction Contracts (ODACC) has been the "emergency room" for payment disputes. It was fast and effective, but for complex, multi-million dollar builds, some felt the roster of adjudicators was too general.
In 2026, the Act introduces Private Adjudication.
- Custom Expertise: Parties can now jointly name a specific expert to act as their adjudicator.
- The Benefit: If you are building a high-tech data centre in Ottawa or a complex marine structure in Simcoe County, you can now choose an adjudicator who is an engineer or lawyer with specific experience in those sub-sectors.
- Finality: Private adjudication carries the same weight as the ODACC roster—the decisions are "interim binding," meaning the money moves now, and you argue the rest in court later (if at all).
Section 3: The 7-Day "Deemed Invoice" Trap
This is the change that is catching the most firms off guard. Under the Prompt Payment rules, the 28-day clock to pay only starts when a "Proper Invoice" is delivered.
Historically, Owners would wait 20 days, then reject the invoice because a backup document was missing, effectively getting a free 20-day extension. That is no longer legal in 2026.
- The 7-Day Limit: An Owner has exactly seven days to dispute an invoice as being "improper."
- The "Deemed" Rule: If the Owner does not issue a formal notice of non-payment or a rejection within those 7 days, the invoice is deemed proper by law. Even if it’s missing data, the payment clock is running.
Conclusion: We can work with General Contractors to implement "Audit-on-Arrival" protocols. If you don't catch an error in the first week, you’ve legally accepted the invoice.
Section 4: Case Study – The "Legacy Project" Confusion
One of the most frequent questions we get at Cabinet Sauvé Law is: "Does this apply to my project that started in 2025?"
The answer lies in the Transition Rules.
This is paragraph text. Click it or hit the Manage Text button to change the font, color, size, format, and more. To set up site-wide paragraph and title styles, go to Site Theme.
- If your contract was signed before January 1, 2026, the new mandatory annual release rules don't kick in until your second anniversary after the law changed.
- Example: For a project started in June 2025, your first mandatory annual release isn't until June 2027. However, on that date, you must release all holdback accrued since the project began. This can create a massive "capital shock" if an Owner hasn't budgeted for a two-year payout at once.
The 2026 Construction Compliance Checklist
To ensure your firm maintains its "Peace of Mind" through this transition, it's recommended to take the following four steps:
- Audit Your Prime Contracts: Ensure your definition of a "Proper Invoice" is robust and includes all 2026 requirements (like WSIB clearances and statutory declarations).
- Set "Anniversary Alerts": Your accounting software needs to flag contract start dates so you don't miss the 14-day Form 6 publication window.
- Review Subcontractor "Flow-Down": Ensure your subcontracts mirror the new annual holdback timelines so you aren't paying out money you haven't received yet.
- Identify Private Adjudicators: For large projects, agree on a "shortlist" of private adjudicators before a dispute arises.
The Cabinet Sauvé Advantage: Boutique Expertise for a Modern Industry
The 2026 Construction Act is designed to reward the organized and penalize the procrastinator. Whether you are an Owner trying to manage a $50M capital budget or a sub-trade trying to get your hard-earned profit out of a holdback account, the "Boutique Advantage" of our firm means we provide the direct, senior-level guidance you need.
We don't just "do law"; we partner with your business to ensure that the legal framework supports your growth. From the streets of Ottawa and Rockland to the growing communities of Barrie, Orillia, Cookstown and Innisfil, we are on the ground helping the builders of Ontario succeed.
Don't let a 7-day deadline or a mandatory anniversary catch you off guard. Contact Cabinet Sauvé Law today for a comprehensive contract audit. Let’s build your future with the Peace of Mind you deserve.










